To use:
* On the Manufacturing Order, set the Analytic Account to use. This may correspond to a Project.
* On Manufacturing Orders, Analytic Items are automatically generated when:
* Raw materials are consumed, or
* Time is spent on work order Operations, with a Work Center with a Cost Type product set.
To analyze costs:
* Go to Manufacturing > Reports > Analytic Items. The cost data is available there and can be used for analysis.
* At Project > Dashboard, "Project Overview" form, a summary of the costs for the corresponding Analytic Account is presented.