To manually run the MRP scheduler:
- Go to Manufacturing > Operations > Run MRP Multi Level.
- On the wizard click Run MRP.
To launch replenishment orders (moves, purchases, production orders...):
- Go to Manufacturing > Operations > MRP Inventory.
- Filter with To procure.
- Select multiple records and click on Action > Procure or click the right hand side gears in any record.
- On the wizard, check everything is ok and click Execute.