Features

  • Show Run MRP Multi Level menu only to a specific new security group Run MRP Manually. (#492)

13.0.1.4.0 (2020-03-26)

  • Add menu entry for planned orders
  • Add button to navigate from planned orders to linked manufacturing orders
  • Add action to convert planned orders to fixed
  • When changing the due date in a planned order the release date is recomputed

13.0.1.3.0 (2020-03-02)

  • [IMP] Minor changes" (#470).
    • Planned Order release and due date become required.
    • Add button to Product MRP Area to update MOQ from Supplier Info.
    • Link Manufacturing Orders with Planned Orders.
    • Allow Mrp Inventory Procure Wizard to be used from other models.
    • Make MRP Inventory creation more extensible.
    • Main Supplier computation (v13 requires explicit False definitions)

13.0.1.2.0 (2020-02-20)

  • [IMP] Minor changes (#468).
    • Planned Orders become fixed on manual creation by default
    • Released Quantity becomes readonly
    • Add product reference if Planned Order name is not defined on bom explosion

13.0.1.1.0 (2020-02-21)

  • [FIX] Minor changes (#469).
    • Fix Main supplier computation in multi company
    • Drop Triplicated field in search view
  • [IMP] Minor changes (#463).
    • Show supply method on MRP Inventory
    • Allow no-MRP users to look into Products

13.0.1.0.0 (2019-12-18)

  • [MIG] Migration to v13.

12.0.1.0.0 (2019-08-05)

  • [MIG] Migration to v12:
    • Estimates as a forecasting mechanism is moved to a new module (mrp_multi_level_estimate).

11.0.3.0.0 (2019-05-22)

  • [REW/IMP] Rework to include Planned Orders. (#365).
  • [IMP] Able to procure from a different location than the area's location.

11.0.2.2.0 (2019-05-02)

  • [IMP] Able to run MRP only for selected areas. (#360).

11.0.2.1.0 (2019-04-02)

  • [IMP] Implement Nbr. Days functionality to be able to group demand when generating supply proposals. (#345).

11.0.2.0.0 (2018-11-20)

  • [REW] Refactor MRP Area. (#322):
    • MRP product concept dropped in favor of Product MRP Area Parameters. This allow to set different MRP parameters for the same product in different areas.
    • Menu items reordering.

11.0.1.1.0 (2018-08-30)

  • [FIX] Consider Qty Multiple on product to propose the quantity to procure. (#297)

11.0.1.0.1 (2018-08-03)

  • [FIX] User and system locales doesn't break MRP calculation. (#290)
  • [FIX] Working Hours are now defined only at Warehouse level and displayed as a related on MRP Areas. (#290)

11.0.1.0.0 (2018-07-09)