When a manufacturing order is created out of a procurement evaluation (from an orderpoint, MTO,...) the calendar is considered in the computation of the planned start date of the manufacturing order.

For example, if it takes 1 day to manufacture a product and it is required for Monday: Replenish

the manufacturing order will be created with planned start date on the previous Friday, if the warehouse operates under a Mo-Fri working calendar. Manufacturing Order

Manual changes to the start or end date of a manufacturing order will also respect the lead time and the warehouse calendar's working days. Manual change day