mirror of
https://github.com/OCA/manufacture.git
synced 2025-01-28 16:37:15 +02:00
756 B
756 B
When a manufacturing order is created out of a procurement evaluation (from an orderpoint, MTO,...) the calendar is considered in the computation of the planned start date of the manufacturing order.
For example, if it takes 1 day to manufacture a product and it is
required for Monday:

the manufacturing order will be created with
planned start date on the previous Friday, if the warehouse operates
under a Mo-Fri working calendar.

Manual changes to the start or end date of a manufacturing order will
also respect the lead time and the warehouse calendar's working days.
