MRP MTO with Stock Purchase
===========================
.. !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
!! This file is generated by oca-gen-addon-readme !!
!! changes will be overwritten. !!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
.. |badge1| image:: https://img.shields.io/badge/maturity-Beta-yellow.png
:target: https://odoo-community.org/page/development-status
:alt: Beta
.. |badge2| image:: https://img.shields.io/badge/licence-AGPL--3-blue.png
:target: http://www.gnu.org/licenses/agpl-3.0-standalone.html
:alt: License: AGPL-3
.. |badge3| image:: https://img.shields.io/badge/github-OCA%2Fmanufacture-lightgray.png?logo=github
:target: https://github.com/OCA/manufacture/tree/10.0/mrp_mto_with_stock_purchase
:alt: OCA/manufacture
.. |badge4| image:: https://img.shields.io/badge/weblate-Translate%20me-F47D42.png
:target: https://translation.odoo-community.org/projects/manufacture-10-0/manufacture-10-0-mrp_mto_with_stock_purchase
:alt: Translate me on Weblate
.. |badge5| image:: https://img.shields.io/badge/runbot-Try%20me-875A7B.png
:target: https://runbot.odoo-community.org/runbot/129/10.0
:alt: Try me on Runbot
|badge1| |badge2| |badge3| |badge4| |badge5|
This module make compatible mrp_mto_with_stock and purchase modules.
Indeed, there is an option in mto_mto_with_stock to check the forecast stock
when checking the availibility of a Manufacture Order. But this forecast stock
does not take into account the quantities coming from draft POs. This module
adds this behavior.
**Table of contents**
.. contents::
:local:
Configuration
=============
* This module is installed automatically when mrp_mto_with_stock and purchase module are installed
Usage
=====
When a manufacturing order is created out of a procurement evaluation
(from an orderpoint, MTO,...) the calendar is considered in the computation
of the planned start date of the manufacturing order.
For example, if it takes 1 day to manufacture a product and it is required
for Monday, the manufacturing order will be created with planned start date
on the previous Friday, if the warehouse operates under a Mo-Fri working
calendar.
Bug Tracker
===========
Bugs are tracked on `GitHub Issues <https://github.com/OCA/manufacture/issues>`_.
In case of trouble, please check there if your issue has already been reported.
If you spotted it first, help us smashing it by providing a detailed and welcomed
`feedback <https://github.com/OCA/manufacture/issues/new?body=module:%20mrp_mto_with_stock_purchase%0Aversion:%2010.0%0A%0A**Steps%20to%20reproduce**%0A-%20...%0A%0A**Current%20behavior**%0A%0A**Expected%20behavior**>`_.
Do not contact contributors directly about support or help with technical issues.
Credits
=======
Authors
~~~~~~~
* Akretion
Contributors
~~~~~~~~~~~~
* * Florian da Costa <florian.dacosta@akretion.com>
Maintainers
~~~~~~~~~~~
This module is maintained by the OCA.
.. image:: https://odoo-community.org/logo.png
:alt: Odoo Community Association
:target: https://odoo-community.org
OCA, or the Odoo Community Association, is a nonprofit organization whose
mission is to support the collaborative development of Odoo features and
promote its widespread use.
This module is part of the `OCA/manufacture <https://github.com/OCA/manufacture/tree/10.0/mrp_mto_with_stock_purchase>`_ project on GitHub.
You are welcome to contribute. To learn how please visit https://odoo-community.org/page/Contribute.