To manually run the MRP scheduler:

  1. Go to Manufacturing > Operations > Run MRP Multi Level.
  2. On the wizard click Run MRP.

To launch replenishment orders (moves, purchases, production orders...):

  1. Go to Manufacturing > Operations > MRP Inventory.
  2. Filter with To procure.
  3. Select multiple records and click on Action > Procure or click the right hand side gears in any record.