Real costs in manufacturing orders
|
||
==================================
|
||
|
||
This module allows to manage the control of Manufacturing Orders actual costs,
|
||
by creating analytic lines as defined in the MO (from *mrp_project*).
|
||
|
||
It also updates product standard price when a manufacturing orders is finished
|
||
according this formula:
|
||
|
||
(Product stock * Product standard price + Production real cost) /
|
||
(Product stock + Final product quantity)
|
||
|
||
Installation
|
||
============
|
||
|
||
This module depends on the module *product_variant_cost_price*, that is
|
||
available in:
|
||
|
||
https://github.com/OCA/product-variant
|
||
|
||
Usage
|
||
=====
|
||
|
||
Processing a manufacture order, analytic entries adding costs will be
|
||
created when:
|
||
|
||
* Some raw material is consumed.
|
||
* A work order is finished or paused.
|
||
* Also, together with *project_timesheet* module, users time is also translated
|
||
to costs in the linked analytic account.
|
||
|
||
The sum of all these analytic entries is the real cost:
|
||
|
||
.. figure:: mrp_production_real_cost/static/description/mrp_real_cost.png
|
||
:alt: MRP Real Cost Details
|
||
|
||
Cost/cycle = all overhead costs associated with running one work centre cycle
|
||
(where a cycle is the Number of Cycles as calculated in the Work Order).
|
||
|
||
Cost/hr = calculated as all overhead costs associated with running the work
|
||
centre (excluding any costs covered in the cost per cycle) / the number of
|
||
hours the work centre is operating.
|
||
|
||
Pre-operation cost = Time before prod. x cost of the Pre-operation costing
|
||
product
|
||
|
||
Post-operation cost = Time after prod. x cost of the Post-operation costing
|
||
product
|
||
|
||
It’s up to the user to determine overhead costs as accurately as possible
|
||
and use all, some or none of them in order to reflect their manufacturing
|
||
process.
|
||
|
||
|
||
.. image:: https://odoo-community.org/website/image/ir.attachment/5784_f2813bd/datas
|
||
:alt: Try me on Runbot
|
||
:target: https://runbot.odoo-community.org/runbot/129/8.0
|
||
|
||
Bug Tracker
|
||
===========
|
||
|
||
Bugs are tracked on `GitHub Issues
|
||
<https://github.com/OCA/manufacture/issues>`_. In case of trouble, please
|
||
check there if your issue has already been reported. If you spotted it first,
|
||
help us smashing it by providing a detailed and welcomed `feedback
|
||
<https://github.com/OCA/
|
||
manufacture/issues/new?body=module:%20
|
||
mrp_production_real_cost%0Aversion:%20
|
||
8.0%0A%0A**Steps%20to%20reproduce**%0A-%20...%0A%0A**Current%20behavior**%0A%0A**Expected%20behavior**>`_.
|
||
|
||
Credits
|
||
=======
|
||
|
||
Contributors
|
||
------------
|
||
|
||
* Pedro M. Baeza <pedro.baeza@serviciosbaeza.com>
|
||
* Ana Juaristi <ajuaristio@gmail.com>
|
||
* Ainara Galdona <agaldona@avanzosc.es>
|
||
* Antonio Espinosa <antonioea@antiun.com>
|
||
|
||
Images
|
||
------
|
||
|
||
* Original Odoo MRP icon
|
||
* Thanks to https://openclipart.org/detail/224801/black-and-white-calculator
|
||
|
||
Maintainer
|
||
----------
|
||
|
||
.. image:: https://odoo-community.org/logo.png
|
||
:alt: Odoo Community Association
|
||
:target: https://odoo-community.org
|
||
|
||
This module is maintained by the OCA.
|
||
|
||
OCA, or the Odoo Community Association, is a nonprofit organization whose
|
||
mission is to support the collaborative development of Odoo features and
|
||
promote its widespread use.
|
||
|
||
To contribute to this module, please visit https://odoo-community.org. |