Commit Graph

16 Commits

Author SHA1 Message Date
OCA-git-bot
dbd7609425 [UPD] changelog 2020-04-09 15:17:51 +00:00
Lois Rilo
fe44649342 document latests feature using fragments 2020-04-09 16:31:27 +02:00
Jordi Ballester Alomar
a909f51e3a Improving the management of planned orders:
* Add menu entry for planned orders
  * Add button to navigate from planned orders to linked manufacturing orders
  * Add action to convert planned orders to fixed
  * When changing the due date in a planned order the release date is recomputed
2020-03-26 11:54:07 +01:00
hveficent
eab1941a5d [IMP] mrp_multi_level:
* Planned Order release and due date become required.
* Add button to Product MRP Area to update MOQ from Supplier Info.
* Link Manufacturing Orders with Planned Orders.
* Allow Mrp Inventory Procure Wizard to be used from other models.
* Make MRP Inventory creation more extensible.
* Main Supplier computation (v13 requires explicit False definitions).
2020-03-11 09:20:58 +01:00
hveficent
476fd79d85 [IMP] mrp_multi_level: Minor changes
* Planned Orders become fixed on manual creation by default
* Released Quantity become readonly
* Add product reference if Planned Order name is not defined on bom explosion
2020-02-28 13:12:36 +01:00
Lois Rilo
d0765c3d87 [13.0][MIG] mrp_multi_level 2019-12-23 10:10:14 +01:00
Lois Rilo
f5483cb563 [12.0][MIG] mrp_multi_level:
* You can know integrate with different forecasting mechanisms.
  As a consequence integration with stock_demand_estimate is moved
  to a new module (mrp_multi_level_estimate).
* As agreed by the authors, the module is re-licensed to LGPL-3.
2019-12-23 10:10:14 +01:00
Lois Rilo
a0445e96b8 [11.0][IMP] mrp_multi_level: able to procure from a different location than area's. 2019-12-23 10:10:14 +01:00
Lois Rilo
6a86bbe7c5 [11.0][REW/IMP] mrp_multi_level:
* Extract concept of planned orders from mrp.move.
* Fix error grouping demand when there is no supply for a the first day of grouping.
* Adapt tests.
2019-12-23 10:10:14 +01:00
Lois Rilo
d224b1931f [11.0][IMP] mrp_multi_level:
* Able to run MRP only for selected areas.
 * Clean logging messages.
2019-12-23 10:10:14 +01:00
Lois Rilo
56b12548b0 [11.0][IMP] mrp_multi_level: be able to group demand when generating supply proposals 2019-12-23 10:10:14 +01:00
Lois Rilo
c0c5fb861f [11.0] mrp_multi_level:
* fix api.depends fields fro main supplier.
 * fix ordering and missing demo file in manifest.
 * Update README.
 * fix action_view* methods.
 * readd hook to exclude in mrp initialization
 * fix computation of qty available (it was considering several times sub-locations).
 * Remove contraint for outoing and incoming moves to be moved in/outside the company, they can be internal transfers.
 * mrp.moves visible with technical settings.
 * Show product and allow to search by it in mrp.inventory.
2019-12-23 10:10:14 +01:00
Lois Rilo
ca6d93ecd6 [11.0][FIX] Consider *Qty Multiple* on product to propose the quantity to procure. 2019-12-23 10:10:14 +01:00
Lois Rilo
d6a2f1fa23 [11.0][FIX] mrp_multi_level:
* calendar defined only in warehouse.
 * remove raw query.
2019-12-23 10:10:14 +01:00
Lois Rilo
e4c0468877 [11.0][FIX] mrp_multi_level: the user and system locales could make the MRP run break. 2019-12-23 10:10:14 +01:00
Lois Rilo
d852b86b4e [11.0][UPD] mrp_multi_level: update README and manifest to OCA standards. 2019-12-23 10:10:14 +01:00