Commit Graph

14 Commits

Author SHA1 Message Date
Matt Taylor
c850eb0bb5 [FIX] mrp_multi_level: fix kit/phantom planning
fixes #1362

Ignoring qty_available for phantom products prevents double counting the
qty_available of components.

Creating planned orders for phantom products is simpler than recursively
exploding phantom BOMs. This also makes it easier to analyze the planning data
generated by the MRP calculation.
2024-12-04 09:42:26 +05:30
BernatPForgeFlow
d4de93f79a [IMP] mrp_multi_level: Add MRP Planner
For each MRP Parameter or for each Product in a MRP Area, we will be able to add a MRP Planner. Once this planner is set, he can filter himself in the MRP Parameters view, MRP Inventory view or MRP Planned Orders view.
2024-12-04 09:42:25 +05:30
Lois Rilo
2d7b0e9450 [IMP] mrp_multi_level: enchance traceability with origin.
* keept description of planned orders verbose.
* make it translatable in most cases.
* while grouping demand include the product in the description.
* add `origin` field not mrp moves and planned orders. Fill it
  with top level demand origin.
2024-12-04 09:42:25 +05:30
Christopher Ormaza
b335a85d2d [15.0][MIG] mrp_multi_level 2024-12-04 09:42:25 +05:30
Jordi Ballester
e4cea8f149 [FIX] mrp_multi_level: allow to delete product.mrp.area records
Planned orders and mrp moves are mostly data that is regenerated every time
that the multi level mrp is run.
2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
15eee3405f Improving the management of planned orders:
* Add menu entry for planned orders
  * Add button to navigate from planned orders to linked manufacturing orders
  * Add action to convert planned orders to fixed
  * When changing the due date in a planned order the release date is recomputed
2024-12-04 09:42:25 +05:30
hveficent
e8cbf54a8d [IMP] mrp_multi_level:
* Planned Order release and due date become required.
* Add button to Product MRP Area to update MOQ from Supplier Info.
* Link Manufacturing Orders with Planned Orders.
* Allow Mrp Inventory Procure Wizard to be used from other models.
* Make MRP Inventory creation more extensible.
* Main Supplier computation (v13 requires explicit False definitions).
2024-12-04 09:42:25 +05:30
hveficent
0da15fcd89 [IMP] mrp_multi_level: Minor changes
* Planned Orders become fixed on manual creation by default
* Released Quantity become readonly
* Add product reference if Planned Order name is not defined on bom explosion
2024-12-04 09:42:25 +05:30
Lois Rilo
8a17a4376f [13.0][MIG] mrp_multi_level 2024-12-04 09:42:25 +05:30
Lois Rilo
2c18d11916 [IMP] mrp_multi_level: black, isort 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
529f39f86c add support for multi-company 2024-12-04 09:42:25 +05:30
Lois Rilo
d750aae31b [12.0][MIG] mrp_multi_level:
* You can know integrate with different forecasting mechanisms.
  As a consequence integration with stock_demand_estimate is moved
  to a new module (mrp_multi_level_estimate).
* As agreed by the authors, the module is re-licensed to LGPL-3.
2024-12-04 09:42:25 +05:30
Lois Rilo
91bee78ae7 [11.0][FIX] mrp_multi_level: fix supply method computation and add required fields. 2024-12-04 09:42:25 +05:30
Lois Rilo
4830795ff4 [11.0][REW/IMP] mrp_multi_level:
* Extract concept of planned orders from mrp.move.
* Fix error grouping demand when there is no supply for a the first day of grouping.
* Adapt tests.
2024-12-04 09:42:25 +05:30