Lois Rilo
3589f59b2a [12.0][FIX] mrp_multi_level: creating undesired planned orders.
add another exclude point at planned order creation.
2024-12-04 09:42:25 +05:30
Lois Rilo
d750aae31b [12.0][MIG] mrp_multi_level:
* You can know integrate with different forecasting mechanisms.
  As a consequence integration with stock_demand_estimate is moved
  to a new module (mrp_multi_level_estimate).
* As agreed by the authors, the module is re-licensed to LGPL-3.
2024-12-04 09:42:25 +05:30
Lois Rilo
82cd356a66 [11.0][MIG] mrp_multi_level: open MRP inventory screen if manually run 2024-12-04 09:42:25 +05:30
Lois Rilo
8ac88a4322 [11.0][IMP] mrp_multi_level: able to group demand estimates or to ignore them. 2024-12-04 09:42:25 +05:30
Lois Rilo
55b8703ea7 [11.0][FIX] mrp_multi_level: pass a context to exclude hook when exploding. 2024-12-04 09:42:25 +05:30
Lois Rilo
4830795ff4 [11.0][REW/IMP] mrp_multi_level:
* Extract concept of planned orders from mrp.move.
* Fix error grouping demand when there is no supply for a the first day of grouping.
* Adapt tests.
2024-12-04 09:42:25 +05:30
Lois Rilo
3300880dea [11.0][IMP] mrp_multi_level:
* Able to run MRP only for selected areas.
 * Clean logging messages.
2024-12-04 09:42:25 +05:30
Lois Rilo
16c495ad49 [11.0][IMP] mrp_multi_level: be able to group demand when generating supply proposals 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
4b1e05da41 Fixes, and add migration script 2024-12-04 09:42:25 +05:30
Lois Rilo
556f49e65f [11.0] mrp_multi_level:
* fix api.depends fields fro main supplier.
 * fix ordering and missing demo file in manifest.
 * Update README.
 * fix action_view* methods.
 * readd hook to exclude in mrp initialization
 * fix computation of qty available (it was considering several times sub-locations).
 * Remove contraint for outoing and incoming moves to be moved in/outside the company, they can be internal transfers.
 * mrp.moves visible with technical settings.
 * Show product and allow to search by it in mrp.inventory.
2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
6374b1ecac [11.0][mrp_multi_level] refactor mrp area 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
6a7f86dd69 convert read_groups into sql queries due to issue with locale 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
fa59cc4a88 mrp_multi_level:
* during bom explosion consider only stockable products in the BOM.
* add logo
* add rounding on application of stock demand estimates.
2024-12-04 09:42:25 +05:30
Lois Rilo
4f168ea7cb [11.0][FIX] mrp_multi_level:
* calendar defined only in warehouse.
 * remove raw query.
2024-12-04 09:42:25 +05:30
Lois Rilo
de40d62221 [11.0][FIX] mrp_multi_level: the user and system locales could make the MRP run break. 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
be9a7a7e22 rename 'date_to_procure' to 'order_release_date' 2024-12-04 09:42:25 +05:30
Jordi Ballester Alomar
2ec080b891 add resource calendar to mrp area 2024-12-04 09:42:25 +05:30
Lois Rilo
5f01dcab14 [11.0] mrp_multi_level: cleanup:
* remove unneded methods
 * fix pylint
 * fix style
2024-12-04 09:42:25 +05:30
Lois Rilo
53130f08cd [11.0][IMP] mrp_multi_level: improve usability 2024-12-04 09:42:25 +05:30
Lois Rilo
1a6b3493c6 [11.0][REN] multi_level_mrp -> mrp_multi_level 2024-12-04 09:42:25 +05:30