Commit Graph

5 Commits

Author SHA1 Message Date
hveficent
ae95609b34 [IMP] mrp_multi_level:
* Planned Order release and due date become required.
* Add button to Product MRP Area to update MOQ from Supplier Info.
* Link Manufacturing Orders with Planned Orders.
* Allow Mrp Inventory Procure Wizard to be used from other models.
* Make MRP Inventory creation more extensible.
* Main Supplier computation (v13 requires explicit False definitions).
2024-03-26 08:57:58 +05:30
Lois Rilo
68a7cb40cb [11.0][REW/IMP] mrp_multi_level:
* Extract concept of planned orders from mrp.move.
* Fix error grouping demand when there is no supply for a the first day of grouping.
* Adapt tests.
2024-03-26 08:57:58 +05:30
Jordi Ballester Alomar
5f213dad8f [11.0][mrp_multi_level] refactor mrp area 2024-03-26 08:57:58 +05:30
Jordi Ballester Alomar
863bb54bce enable MRP view in product templates 2024-03-26 08:57:58 +05:30
Lois Rilo
4de1899aa1 [11.0][REN] multi_level_mrp -> mrp_multi_level 2024-03-26 08:57:58 +05:30