Jordi Ballester Alomar
|
0242f8aecb
|
mrp_multi_level:
* during bom explosion consider only stockable products in the BOM.
* add logo
* add rounding on application of stock demand estimates.
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
05a361c7b1
|
[11.0][FIX] Consider *Qty Multiple* on product to propose the quantity to procure.
|
2021-03-03 13:04:05 +01:00 |
|
Jordi Ballester Alomar
|
d313466f1b
|
enable MRP view in product templates
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
70f87e9b10
|
Translated using Weblate (Spanish)
Currently translated at 84.2% (117 of 139 strings)
Translation: manufacture-11.0/manufacture-11.0-mrp_multi_level
Translate-URL: https://translation.odoo-community.org/projects/manufacture-11-0/manufacture-11-0-mrp_multi_level/es/
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
a03fc8c81b
|
Added translation using Weblate (Spanish)
|
2021-03-03 13:04:05 +01:00 |
|
OCA Git Bot
|
9cc132f936
|
[UPD] README.rst
|
2021-03-03 13:04:05 +01:00 |
|
OCA Git Bot
|
ae67a10646
|
[UPD] README.rst
|
2021-03-03 13:04:05 +01:00 |
|
oca-travis
|
8d3938fd80
|
[UPD] Update mrp_multi_level.pot
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
5e3882d61d
|
[11.0][FIX] mrp_multi_level:
* calendar defined only in warehouse.
* remove raw query.
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
53e14e7936
|
[11.0][FIX] mrp_multi_level: the user and system locales could make the MRP run break.
|
2021-03-03 13:04:05 +01:00 |
|
OCA Git Bot
|
cc2fbdf126
|
[UPD] README.rst
|
2021-03-03 13:04:05 +01:00 |
|
oca-travis
|
40bf2ba865
|
[UPD] Update mrp_multi_level.pot
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
4bceabe96d
|
[11.0][UPD] mrp_multi_level: update README and manifest to OCA standards.
|
2021-03-03 13:04:05 +01:00 |
|
Jordi Ballester Alomar
|
7c0296a673
|
rename 'date_to_procure' to 'order_release_date'
|
2021-03-03 13:04:05 +01:00 |
|
Jordi Ballester Alomar
|
d857366eb4
|
add dependency with mrp_working_calendar
|
2021-03-03 13:04:05 +01:00 |
|
Jordi Ballester Alomar
|
4e189e9034
|
change date_to_procure to consider working calendar
|
2021-03-03 13:04:05 +01:00 |
|
Jordi Ballester Alomar
|
ccbae558f2
|
add resource calendar to mrp area
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
307d495db3
|
[11.0][ADD] mrp_multi_level: ods with the result expected from the mrp run with the test environment.
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
cde17288a6
|
[11.0][IMP] mrp_multi_level: reduce qty to procure with each procure done.
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
70966480af
|
[11.0] mrp_multi_level: cleanup:
* remove unneded methods
* fix pylint
* fix style
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
ff124b2e2b
|
[11.0][IMP] mrp_multi_level: improve usability
|
2021-03-03 13:04:05 +01:00 |
|
Lois Rilo
|
a49f269bf0
|
[11.0][REN] multi_level_mrp -> mrp_multi_level
|
2021-03-03 13:04:05 +01:00 |
|