diff --git a/mrp_warehouse_calendar/README.rst b/mrp_warehouse_calendar/README.rst index d66596b1f..58a36dc5b 100644 --- a/mrp_warehouse_calendar/README.rst +++ b/mrp_warehouse_calendar/README.rst @@ -17,21 +17,22 @@ MRP Warehouse Calendar :target: http://www.gnu.org/licenses/lgpl-3.0-standalone.html :alt: License: LGPL-3 .. |badge3| image:: https://img.shields.io/badge/github-OCA%2Fmanufacture-lightgray.png?logo=github - :target: https://github.com/OCA/manufacture/tree/16.0/mrp_warehouse_calendar + :target: https://github.com/OCA/manufacture/tree/17.0/mrp_warehouse_calendar :alt: OCA/manufacture .. |badge4| image:: https://img.shields.io/badge/weblate-Translate%20me-F47D42.png - :target: https://translation.odoo-community.org/projects/manufacture-16-0/manufacture-16-0-mrp_warehouse_calendar + :target: https://translation.odoo-community.org/projects/manufacture-17-0/manufacture-17-0-mrp_warehouse_calendar :alt: Translate me on Weblate .. |badge5| image:: https://img.shields.io/badge/runboat-Try%20me-875A7B.png - :target: https://runboat.odoo-community.org/builds?repo=OCA/manufacture&target_branch=16.0 + :target: https://runboat.odoo-community.org/builds?repo=OCA/manufacture&target_branch=17.0 :alt: Try me on Runboat |badge1| |badge2| |badge3| |badge4| |badge5| -With this module the manufacturing orders created from procurements consider -the calendar assigned to the warehouse of the picking type of the -manufacturing order to determine, based on the product's manufacturing -lead time, the planned start date of the manufacturing order. +With this module the manufacturing orders created from procurements +consider the calendar assigned to the warehouse of the picking type of +the manufacturing order to determine, based on the product's +manufacturing lead time, the planned start date of the manufacturing +order. Further manual replannings of start/end date of the manufacturing order also consider the lead time using the warehouse calendar days. @@ -44,27 +45,25 @@ also consider the lead time using the warehouse calendar days. Configuration ============= -* This module depends on `stock_warehouse_calendar `_ - -* Go to *Settings* and activate the developer mode. - -* Go to *Settings > Technical > Resource > Working Time* and define your - resource calendar. - -* Go to *Inventory > Configuration > Warehouse Management > Warehouses* - and assign the Resource Calendar. +- This module depends on + `stock_warehouse_calendar `__ +- Go to *Settings* and activate the developer mode. +- Go to *Settings > Technical > Resource > Working Time* and define + your resource calendar. +- Go to *Inventory > Configuration > Warehouse Management > Warehouses* + and assign the Resource Calendar. Usage ===== When a manufacturing order is created out of a procurement evaluation -(from an orderpoint, MTO,...) the calendar is considered in the computation -of the planned start date of the manufacturing order. +(from an orderpoint, MTO,...) the calendar is considered in the +computation of the planned start date of the manufacturing order. -For example, if it takes 1 day to manufacture a product and it is required -for Monday, the manufacturing order will be created with planned start date -on the previous Friday, if the warehouse operates under a Mo-Fri working -calendar. +For example, if it takes 1 day to manufacture a product and it is +required for Monday, the manufacturing order will be created with +planned start date on the previous Friday, if the warehouse operates +under a Mo-Fri working calendar. Bug Tracker =========== @@ -72,7 +71,7 @@ Bug Tracker Bugs are tracked on `GitHub Issues `_. In case of trouble, please check there if your issue has already been reported. If you spotted it first, help us to smash it by providing a detailed and welcomed -`feedback `_. +`feedback `_. Do not contact contributors directly about support or help with technical issues. @@ -80,18 +79,18 @@ Credits ======= Authors -~~~~~~~ +------- * ForgeFlow Contributors -~~~~~~~~~~~~ +------------ -* Jordi Ballester -* Lois Rilo +- Jordi Ballester +- Lois Rilo Maintainers -~~~~~~~~~~~ +----------- This module is maintained by the OCA. @@ -111,6 +110,6 @@ Current `maintainer `__: |maintainer-JordiBForgeFlow| -This module is part of the `OCA/manufacture `_ project on GitHub. +This module is part of the `OCA/manufacture `_ project on GitHub. You are welcome to contribute. To learn how please visit https://odoo-community.org/page/Contribute. diff --git a/mrp_warehouse_calendar/pyproject.toml b/mrp_warehouse_calendar/pyproject.toml new file mode 100644 index 000000000..4231d0ccc --- /dev/null +++ b/mrp_warehouse_calendar/pyproject.toml @@ -0,0 +1,3 @@ +[build-system] +requires = ["whool"] +build-backend = "whool.buildapi" diff --git a/mrp_warehouse_calendar/readme/CONFIGURE.md b/mrp_warehouse_calendar/readme/CONFIGURE.md new file mode 100644 index 000000000..c4414f162 --- /dev/null +++ b/mrp_warehouse_calendar/readme/CONFIGURE.md @@ -0,0 +1,7 @@ +- This module depends on + [stock_warehouse_calendar](https://github.com/OCA/stock-logistics-warehouse) +- Go to *Settings* and activate the developer mode. +- Go to *Settings \> Technical \> Resource \> Working Time* and define + your resource calendar. +- Go to *Inventory \> Configuration \> Warehouse Management \> + Warehouses* and assign the Resource Calendar. diff --git a/mrp_warehouse_calendar/readme/CONFIGURE.rst b/mrp_warehouse_calendar/readme/CONFIGURE.rst deleted file mode 100644 index 16ab5b81e..000000000 --- a/mrp_warehouse_calendar/readme/CONFIGURE.rst +++ /dev/null @@ -1,9 +0,0 @@ -* This module depends on `stock_warehouse_calendar `_ - -* Go to *Settings* and activate the developer mode. - -* Go to *Settings > Technical > Resource > Working Time* and define your - resource calendar. - -* Go to *Inventory > Configuration > Warehouse Management > Warehouses* - and assign the Resource Calendar. diff --git a/mrp_warehouse_calendar/readme/CONTRIBUTORS.md b/mrp_warehouse_calendar/readme/CONTRIBUTORS.md new file mode 100644 index 000000000..ef0489c75 --- /dev/null +++ b/mrp_warehouse_calendar/readme/CONTRIBUTORS.md @@ -0,0 +1,2 @@ +- Jordi Ballester \<\> +- Lois Rilo \<\> diff --git a/mrp_warehouse_calendar/readme/CONTRIBUTORS.rst b/mrp_warehouse_calendar/readme/CONTRIBUTORS.rst deleted file mode 100644 index 8cc067b15..000000000 --- a/mrp_warehouse_calendar/readme/CONTRIBUTORS.rst +++ /dev/null @@ -1,2 +0,0 @@ -* Jordi Ballester -* Lois Rilo diff --git a/mrp_warehouse_calendar/readme/DESCRIPTION.md b/mrp_warehouse_calendar/readme/DESCRIPTION.md new file mode 100644 index 000000000..100b2da2b --- /dev/null +++ b/mrp_warehouse_calendar/readme/DESCRIPTION.md @@ -0,0 +1,8 @@ +With this module the manufacturing orders created from procurements +consider the calendar assigned to the warehouse of the picking type of +the manufacturing order to determine, based on the product's +manufacturing lead time, the planned start date of the manufacturing +order. + +Further manual replannings of start/end date of the manufacturing order +also consider the lead time using the warehouse calendar days. diff --git a/mrp_warehouse_calendar/readme/DESCRIPTION.rst b/mrp_warehouse_calendar/readme/DESCRIPTION.rst deleted file mode 100644 index 1c29d471f..000000000 --- a/mrp_warehouse_calendar/readme/DESCRIPTION.rst +++ /dev/null @@ -1,7 +0,0 @@ -With this module the manufacturing orders created from procurements consider -the calendar assigned to the warehouse of the picking type of the -manufacturing order to determine, based on the product's manufacturing -lead time, the planned start date of the manufacturing order. - -Further manual replannings of start/end date of the manufacturing order -also consider the lead time using the warehouse calendar days. diff --git a/mrp_warehouse_calendar/readme/USAGE.md b/mrp_warehouse_calendar/readme/USAGE.md new file mode 100644 index 000000000..238bc0c91 --- /dev/null +++ b/mrp_warehouse_calendar/readme/USAGE.md @@ -0,0 +1,8 @@ +When a manufacturing order is created out of a procurement evaluation +(from an orderpoint, MTO,...) the calendar is considered in the +computation of the planned start date of the manufacturing order. + +For example, if it takes 1 day to manufacture a product and it is +required for Monday, the manufacturing order will be created with +planned start date on the previous Friday, if the warehouse operates +under a Mo-Fri working calendar. diff --git a/mrp_warehouse_calendar/readme/USAGE.rst b/mrp_warehouse_calendar/readme/USAGE.rst deleted file mode 100644 index 081b0392d..000000000 --- a/mrp_warehouse_calendar/readme/USAGE.rst +++ /dev/null @@ -1,8 +0,0 @@ -When a manufacturing order is created out of a procurement evaluation -(from an orderpoint, MTO,...) the calendar is considered in the computation -of the planned start date of the manufacturing order. - -For example, if it takes 1 day to manufacture a product and it is required -for Monday, the manufacturing order will be created with planned start date -on the previous Friday, if the warehouse operates under a Mo-Fri working -calendar. diff --git a/mrp_warehouse_calendar/static/description/index.html b/mrp_warehouse_calendar/static/description/index.html index 63de7538b..85b623854 100644 --- a/mrp_warehouse_calendar/static/description/index.html +++ b/mrp_warehouse_calendar/static/description/index.html @@ -369,11 +369,12 @@ ul.auto-toc { !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! !! source digest: sha256:ff4d842f23c3df422ec667756bc7cf292229ece485361f1a5caea6ee46b47a8a !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! --> -

Production/Stable License: LGPL-3 OCA/manufacture Translate me on Weblate Try me on Runboat

-

With this module the manufacturing orders created from procurements consider -the calendar assigned to the warehouse of the picking type of the -manufacturing order to determine, based on the product’s manufacturing -lead time, the planned start date of the manufacturing order.

+

Production/Stable License: LGPL-3 OCA/manufacture Translate me on Weblate Try me on Runboat

+

With this module the manufacturing orders created from procurements +consider the calendar assigned to the warehouse of the picking type of +the manufacturing order to determine, based on the product’s +manufacturing lead time, the planned start date of the manufacturing +order.

Further manual replannings of start/end date of the manufacturing order also consider the lead time using the warehouse calendar days.

Table of contents

@@ -393,10 +394,11 @@ also consider the lead time using the warehouse calendar days.

Configuration

    -
  • This module depends on stock_warehouse_calendar
  • +
  • This module depends on +stock_warehouse_calendar
  • Go to Settings and activate the developer mode.
  • -
  • Go to Settings > Technical > Resource > Working Time and define your -resource calendar.
  • +
  • Go to Settings > Technical > Resource > Working Time and define +your resource calendar.
  • Go to Inventory > Configuration > Warehouse Management > Warehouses and assign the Resource Calendar.
@@ -404,19 +406,19 @@ and assign the Resource Calendar.

Usage

When a manufacturing order is created out of a procurement evaluation -(from an orderpoint, MTO,…) the calendar is considered in the computation -of the planned start date of the manufacturing order.

-

For example, if it takes 1 day to manufacture a product and it is required -for Monday, the manufacturing order will be created with planned start date -on the previous Friday, if the warehouse operates under a Mo-Fri working -calendar.

+(from an orderpoint, MTO,…) the calendar is considered in the +computation of the planned start date of the manufacturing order.

+

For example, if it takes 1 day to manufacture a product and it is +required for Monday, the manufacturing order will be created with +planned start date on the previous Friday, if the warehouse operates +under a Mo-Fri working calendar.

Bug Tracker

Bugs are tracked on GitHub Issues. In case of trouble, please check there if your issue has already been reported. If you spotted it first, help us to smash it by providing a detailed and welcomed -feedback.

+feedback.

Do not contact contributors directly about support or help with technical issues.

@@ -443,7 +445,7 @@ mission is to support the collaborative development of Odoo features and promote its widespread use.

Current maintainer:

JordiBForgeFlow

-

This module is part of the OCA/manufacture project on GitHub.

+

This module is part of the OCA/manufacture project on GitHub.

You are welcome to contribute. To learn how please visit https://odoo-community.org/page/Contribute.